In the game, this was cooking dinnerPlay “When’s Dinner Ready?”
| In the game | In real IT |
|---|---|
| Cooking steps and minutes | Tasks and days |
| Cooking-step diagram | Arrow diagram |
| Time until dinner | Shortest project duration |
| The longest chain | Critical path |
| Dotted “just wait” arrow | Dummy activity |
Arrows are tasks, circles are milestones
Each arrow is one task, and the number beside it is how many days it takes. A circle (node) is a milestone: tasks leaving a circle can’t start until all the tasks arriving at it are done.
The longest path is the project’s length
Add up the days along each path from start to goal and compare. In the diagram above, A→C takes 7 days and B→D takes 8. For every task to finish, you need the 8 days of the longest path. This path is the critical path.
The critical path can’t slip
If a task on the critical path is 1 day late, the whole project is 1 day late. The other paths, meanwhile, have slack: in the diagram, A→C can be up to 1 day late without affecting the total. And if you want to shorten the schedule, it only helps to shorten tasks on the critical path.
- Arrows are tasks; a task starts only after every task entering its circle is done
- The longest path is the critical path and sets the shortest schedule
- Any delay on the critical path delays the whole project