Arrow diagrams and the critical path

An arrow diagram shows the order and duration of tasks with arrows. The path that takes the most days is called the “critical path,” and it is the shortest time the whole project can take.

Reading time: about 1 min

More in the 5-min version →

In the game, this was cooking dinnerPlay “When’s Dinner Ready?”

In the gameIn real IT
Cooking steps and minutesTasks and days
Cooking-step diagramArrow diagram
Time until dinnerShortest project duration
The longest chainCritical path
Dotted “just wait” arrowDummy activity
S12GA 3dC 4dB 5dD 3dA→C is 7 days, B→D is 8 days
The longest, B→D (8 days), is the critical path. The whole project can’t finish in under 8 days

Arrows are tasks, circles are milestones

Each arrow is one task, and the number beside it is how many days it takes. A circle (node) is a milestone: tasks leaving a circle can’t start until all the tasks arriving at it are done.

The longest path is the project’s length

Add up the days along each path from start to goal and compare. In the diagram above, A→C takes 7 days and B→D takes 8. For every task to finish, you need the 8 days of the longest path. This path is the critical path.

The critical path can’t slip

If a task on the critical path is 1 day late, the whole project is 1 day late. The other paths, meanwhile, have slack: in the diagram, A→C can be up to 1 day late without affecting the total. And if you want to shorten the schedule, it only helps to shorten tasks on the critical path.

Summary
  • Arrows are tasks; a task starts only after every task entering its circle is done
  • The longest path is the critical path and sets the shortest schedule
  • Any delay on the critical path delays the whole project
Go further: 5-min deep diveThe critical path in depth: node times and dummy tasksHow to find the “earliest and latest node times” so busy diagrams don’t trip you up, dotted dummy tasks, and how to think about shortening a schedule.Read the 5-min version →