Labels on “both ends,” with “both destinations”
Put labels on both ends of a cable. With a label on only one, you can’t tell from the other end where it goes. Write both locations: this end and the far end.
R03-21U-NIC1 ⇔ R05-SW01-P12 A cable connecting NIC1 of the server at 21U in rack R03 to port 12 of switch 01 in rack R05
Written like this, you can tell the other end right away, whichever end you look at.
Tell them apart at a glance by color
If you assign cable colors by role, you can tell them apart without reading labels. Color rules differ from company to company, but here’s an example:
| Color (example) | Role |
|---|---|
| Blue | Ordinary data traffic |
| Yellow | Management (iDRAC, etc.) |
| Green | Storage |
| Red | High impact if stopped — check before touching |
Separate power cables too, such as black for feed A and gray for feed B, and you won’t hesitate over “which one can I unplug for the feed-B work?”
Bundle “gently”
- Overtightening cable ties crushes the cable and disturbs the twist of the pairs inside, causing transmission errors. Optical fiber can even break
- That’s why hook-and-loop (Velcro-style) straps, which can be attached and removed any number of times, are widely used
- Never bend optical fiber sharply. It has a set minimum radius it may be bent to (the minimum bend radius)
- Route power cables and LAN cables as far apart as possible (so they don’t pick up power noise)
Leave enough length to pull the server out
Many rack servers slide out on rails so parts can be replaced. If the cables at the back are short and pulled taut, they come out the moment you slide the server out. So you fit a cable management arm, a folding arm that carries the cables, or leave just enough slack to slide it out. Finding the length that’s neither “excess” nor too short to “pull out” is where skill shows.
When you change cabling, update the cabling chart (the list of which port connects to which) the same day. If the chart and reality drift apart, nobody trusts the chart, and you end up tracing cables one by one by eye. The basic rule is to check the chart against reality at the end of the job before you go home.
Practice questions
Four-choice questions in the style of Japan’s Fundamental Information Technology Engineer Examination. Tap below to see the answer.
Q1Which is the most appropriate way to label cables?
- AWrite the cable number on the device end only
- BOn both ends, write the connection points of this end and the far end
- CPut a single label in the middle of the cable
- DUse no labels and manage it all with the cabling chart
Show the answer and explanation
Answer: BIf both ends show both connection points, you can tell the other end right away from either end.
Q2Which is an appropriate precaution when bundling LAN cables and optical fiber?
- ATighten cable ties as hard as possible
- BCoil optical fiber tightly into small loops
- CBundle them without overtightening or overbending
- DBind them tightly together with power cables
Show the answer and explanation
Answer: CTightening hard crushes cables, and bending optical fiber sharply leaks light or breaks it. Keeping them away from power cables is basic practice.
Q3On a server with two power supply units, what is the main purpose of using different colors for the feed-A and feed-B power cables?
- ATo make it look uniform
- BTo avoid unplugging the wrong cable during work that stops only one feed
- CTo lower the electricity bill
- DTo make the cables last longer
Show the answer and explanation
Answer: BWhen work is done one feed at a time, telling them apart by color prevents accidents where you unplug a cable on the feed that must not stop.
- Label both ends with both connection points
- Color coding shows roles and power feeds at a glance
- Don’t overtighten, don’t overbend, and leave enough length to pull out. Keep the cabling chart matching reality